[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1162038":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1162038,822,2,"多选题","已知工程结构类型及建设面积匡算主要材料需用量时，必需的数据是（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","工程的建筑面积",true,{"key":16,"text":17,"correct":14},"B","该种材料消耗定额",{"key":19,"text":20,"correct":14},"C","调整系数",{"key":22,"text":23,"correct":24},"D","每万元工程量该种材料消耗定额",false,{"key":26,"text":27,"correct":24},"E","工程项目总投资","ABC","已知工程结构类型及建设面积匡算主要材料需用量时，必需的数据是工程的建筑面积；该类工程单位建筑面积该种材料消耗定额，调整系数。",{"id":6,"name":31,"category":32,"favorite":33},"(材料员)专业管理实务 岗位知识","建筑工程",0]