[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1162034":3},{"question":4,"library":25},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":23,"analysis":24},1162034,822,2,"多选题","采用直接计算法计算施工项目某种材料计划需用量时，可采用的定额为（ ）。 A.材料消耗施工定额 B.概算定额。 C.月度计划 D.旬计划",[11,14,16,19,21],{"key":12,"text":12,"correct":13},"A",true,{"key":15,"text":15,"correct":13},"B",{"key":17,"text":17,"correct":18},"C",false,{"key":20,"text":20,"correct":18},"D",{"key":22,"text":22,"correct":18},"E","AB","采用直接计算法计算施工项目某种材料计划需用量时，可采用的定额为材料消耗施工定额和概算定额。",{"id":6,"name":26,"category":27,"favorite":28},"(材料员)专业管理实务 岗位知识","建筑工程",0]