[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1162031":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1162031,822,2,"多选题","建筑材料计划按用途分类有需用量计划、采购计划、供应计划、加工订货计划、施工设置用料计划、还包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","周转材料租赁计划",true,{"key":16,"text":17,"correct":18},"B","实施计划",false,{"key":20,"text":21,"correct":14},"C","主要材料节约计划",{"key":23,"text":24,"correct":18},"D","运输计划",{"key":26,"text":27,"correct":18},"E","检测计划","AC","建筑材料计划按用途分类有需用量计划、采购计划、供应计划、加工订货计划、施工设置用料计划、还包括周转材料租赁计划、主要材料节约计划。",{"id":6,"name":31,"category":32,"favorite":33},"(材料员)专业管理实务 岗位知识","建筑工程",0]