[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1162025":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1162025,822,2,"多选题","下列（ ）不属于材料计划变更和修订主要的方法。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","全面调整或修订",false,{"key":16,"text":17,"correct":14},"B","专案调整或修订",{"key":19,"text":20,"correct":14},"C","临时调整或修订",{"key":22,"text":23,"correct":24},"D","施工进度调整",true,{"key":26,"text":27,"correct":24},"E","工艺变更设计","DE","施工进度调整、工艺变更设计不属于材料计划变更和修订主要的方法。",{"id":6,"name":31,"category":32,"favorite":33},"(材料员)专业管理实务 岗位知识","建筑工程",0]