[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1162021":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1162021,822,2,"多选题","材料消耗定额的制定方法比较常用的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","计算法",true,{"key":16,"text":17,"correct":14},"B","统计分析法",{"key":19,"text":20,"correct":14},"C","经验估计法",{"key":22,"text":23,"correct":24},"D","间接计算法",false,{"key":26,"text":27,"correct":24},"E","现场测定法","ABC","材料消耗定额的制定方法比较常用的有计算法、统计分析法、经验估计法。",{"id":6,"name":31,"category":32,"favorite":33},"(材料员)专业管理实务 岗位知识","建筑工程",0]