[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1162017":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1162017,822,2,"多选题","单位工程施工机械需用量计算是根据（ ）编制的。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","单位工程工程量",true,{"key":16,"text":17,"correct":18},"B","设计方案",false,{"key":20,"text":21,"correct":14},"C","施工方案",{"key":23,"text":24,"correct":14},"D","施工机具类型",{"key":26,"text":27,"correct":14},"E","定额机械台班用量","ACDE","单位工程施工机械需用量计算是根据单位工程工程量、施工方案、施工机具类型及定额机械台班用量编制的。",{"id":6,"name":31,"category":32,"favorite":33},"(材料员)专业管理实务 岗位知识","建筑工程",0]