[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1162009":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1162009,822,2,"多选题","检查材料供应的及时性，需要把诸如（ ）等资料联系起来考查。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","时间",true,{"key":16,"text":17,"correct":14},"B","数量",{"key":19,"text":20,"correct":14},"C","期初库存量",{"key":22,"text":23,"correct":24},"D","损耗量",false,{"key":26,"text":27,"correct":14},"E","平均每天需用量","ABCE","在检查考核材料供应计划的执行情况时，还可能出现材料供应数量充足，而因材料供 应不及时而影响施工生产正常进行的情况。所以还应检查材料供应的及时性，需要把时间、数量、平均每天需用量和期初库存量等资料联系起来考查。",{"id":6,"name":31,"category":32,"favorite":33},"(材料员)专业管理实务 岗位知识","建筑工程",0]