[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1162004":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1162004,822,2,"多选题","设备材料采购或力旺时注意材料实际成本核算，采购时必须进行比较的内容包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","同样的材料比价格",false,{"key":16,"text":17,"correct":14},"B","同样的质量比运距",{"key":19,"text":20,"correct":21},"C","同样的材料比质量",true,{"key":23,"text":24,"correct":21},"D","同样的质量比价格",{"key":26,"text":27,"correct":21},"E","同样价格比运距","CDE","设备材料采购或力旺时注意材料实际成本核算，采购时必须进行比较的内容包括同样的材料比质量、同样的质量比价格、同样价格比运距。",{"id":6,"name":31,"category":32,"favorite":33},"(材料员)专业管理实务 岗位知识","建筑工程",0]