[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1162001":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1162001,822,2,"多选题","材料供应计划完成率用于考核材料在某一时期供应计划的完成情况，跟材料供应计划完成率有关的因素有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","库存量",false,{"key":16,"text":17,"correct":18},"B","实际收人量",true,{"key":20,"text":21,"correct":18},"C","计划收人量",{"key":23,"text":24,"correct":14},"D","使用额",{"key":26,"text":27,"correct":14},"E","期初库存量","BC","材料供应计划完成率用于考核材料在某一时期供应计划的完成情况，跟材料供应计划完成率有关的因素有实际收人量、计划收人量。",{"id":6,"name":31,"category":32,"favorite":33},"(材料员)专业管理实务 岗位知识","建筑工程",0]