[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1161986":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1161986,822,2,"多选题","每批石子进场验收时，应进行（ ）检验。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","颗粒级配",true,{"key":16,"text":17,"correct":14},"B","含泥量",{"key":19,"text":20,"correct":14},"C","泥块含量",{"key":22,"text":23,"correct":14},"D","针、片状含量",{"key":25,"text":26,"correct":27},"E","压碎指标",false,"ABCD","每批石子进场验收时，应进行颗粒级配、含泥量、泥块含量、针、片状含量检验。",{"id":6,"name":31,"category":32,"favorite":33},"(材料员)专业管理实务 岗位知识","建筑工程",0]