[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1161927":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1161927,822,2,"多选题","周转材料管理的核算包括（ ）等核算方式。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","成本核算",false,{"key":16,"text":17,"correct":18},"B","统计核算",true,{"key":20,"text":21,"correct":18},"C","业务核算",{"key":23,"text":24,"correct":18},"D","会计核算",{"key":26,"text":27,"correct":14},"E","经济核算","BCD","周转材料一次摊销法摊销与核算的结果会使价值较大、使用期限较长的周转材料的价值管理与实物管理相脱节，即周转材料的价值已全部转入工程成本中但实物仍然存在。由于已领用的周转材料价值已不在账上有记录了，所以使其变成了账外资产，从而使周转材料的价值管理与实物管理脱节，不利于对周转材料的管理。",{"id":6,"name":31,"category":32,"favorite":33},"(材料员)专业管理实务 岗位知识","建筑工程",0]