[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1161907":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1161907,822,2,"多选题","按照《施工合同文本》规定，在施工中由于（ ）造成工期延误，经发包人代表确认，竣工日期可以顺延。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","承包人未能及时调配施工机械",false,{"key":16,"text":17,"correct":18},"B","发生不可抗力",true,{"key":20,"text":21,"correct":14},"C","雨季天数增多",{"key":23,"text":24,"correct":18},"D","工程量变化和设计变更",{"key":26,"text":27,"correct":18},"E","一周内非承包人原因停电、停水、停气等造成停工累计超过8小时","BDE","1．可以顺延工期的条件。（4）设计变更和工程量增加；（5）一周内非承包人原因停水、停电、停气造成停工累计超过8h；（6）不可抗力。以上情况可以顺延的根本原因在于，这些情况属于发包人违约或者是应当由发包人承担的风险。反之，如果造成工期延误的原因是承包人的违约或者应当由承包人承担的风险，则工期不能顺延。",{"id":6,"name":31,"category":32,"favorite":33},"(材料员)专业管理实务 岗位知识","建筑工程",0]