[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1161889":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1161889,822,2,"多选题","工程实际进度与进度计划不符时，承包人应当按照工程师的要求提出改进措施（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","需经工程师确认后才能执行",true,{"key":16,"text":17,"correct":14},"B","因承包人自身的原因造成工程实际进度与经确认的进度计划不符的，所有后果都由承包商自行承担",{"key":19,"text":20,"correct":21},"C","因承包人自身原因造成的，工程师只对改进措施的效果负责",false,{"key":23,"text":24,"correct":21},"D","采用改进措施后，必须顺延工期",{"key":26,"text":27,"correct":21},"E","改进措施后，进度仍然不符的，工程师可以要求承包人修改进度计划，并经工程师确认，这种确认是工程师对工程延期的批准","AB","工程实际进度与进度计划不符时，承包人应当按照工程师的要求提出改进措施需经工程师确认后才能执行。",{"id":6,"name":31,"category":32,"favorite":33},"(材料员)专业管理实务 岗位知识","建筑工程",0]