[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1161752":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1161752,822,1,"单选题","（ ）主要是要控制轴线位置尺寸、标高、模板尺寸及墙体洞口留设等方面，从而防止因施工偏差而返工。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","编制施工组织设计",false,{"key":16,"text":17,"correct":14},"B","施工图纸会审工作",{"key":19,"text":20,"correct":14},"C","技术交底工作",{"key":22,"text":23,"correct":24},"D","施工的预检工作",true,"施工的预检工作主要是要控制轴线位置尺寸、标高、模板尺寸及墙体洞口留设等方面，从而防止因施工偏差而返工。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)专业管理实务 岗位知识","建筑工程",0]