[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1161625":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1161625,822,1,"单选题","现场施工粉煤灰混凝土的坍落度的检验，每工作班至少测定（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","一",false,{"key":16,"text":17,"correct":18},"B","两",true,{"key":20,"text":21,"correct":14},"C","三",{"key":23,"text":24,"correct":14},"D","四","现场施工粉煤灰混凝土的坍落度的检验，每工作班至少测定两。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)专业管理实务 岗位知识","建筑工程",0]