[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1161582":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1161582,822,1,"单选题","机电设备采购分标时不需要考虑的因素为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","招标项目的规模",false,{"key":16,"text":17,"correct":14},"B","工程进度与供货时间",{"key":19,"text":20,"correct":14},"C","市场供应情况",{"key":22,"text":23,"correct":24},"D","售后服务",true,"除了售后服务，其他都是机电设备采购分标时需要考虑的因素。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)专业管理实务 岗位知识","建筑工程",0]