[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1161556":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1161556,822,1,"单选题","下列（ ）不是影响材料计划实现的因素。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工任务改变",false,{"key":16,"text":17,"correct":14},"B","采购情况改变",{"key":19,"text":20,"correct":14},"C","施工进度变化",{"key":22,"text":23,"correct":24},"D","材料价格变化",true,"材料价格变化不是影响材料计划实现的因素。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)专业管理实务 岗位知识","建筑工程",0]