[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1161554":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1161554,822,1,"单选题","（ ）的消耗定额，应该按照多次使用，分次摊销的方法确定。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","周转材料",true,{"key":16,"text":17,"correct":18},"B","小宗材料",false,{"key":20,"text":21,"correct":18},"C","大宗材料",{"key":23,"text":24,"correct":18},"D","混凝土","周转材料的消耗定额，应该按照多次使用，分次摊销的方法确定。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)专业管理实务 岗位知识","建筑工程",0]