[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1161530":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1161530,822,1,"单选题","变更或修订材料计划的情况中，下列（ ）不属于任务量变化引起的。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在项目实施过程中，由于技术革新，增加了新的材料品种",false,{"key":16,"text":17,"correct":18},"B","设计变更必然引起工艺变更，材料消耗可能与原来不一样，材料计戈刂也要相应调整",true,{"key":20,"text":21,"correct":14},"C","图纸和技术资料尚不齐全清况下，材料实际需要与原概算有出人，需要调整材料计划",{"key":23,"text":24,"correct":14},"D","在工具和设备修理中，实际修理所用的材料与原计划中申请的材料有出人","设计变更必然引起工艺变更，材料消耗可能与原来不一样，材料计戈刂也要相应调整不属于任务量变化引起的。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)专业管理实务 岗位知识","建筑工程",0]