[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1161528":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1161528,822,1,"单选题","加工订货计划的具体形式是订货明细表，它不包括（ ）内容。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","材料名称、规格、型号",false,{"key":16,"text":17,"correct":14},"B","技术要求、质量标准、数量、交货时间",{"key":19,"text":20,"correct":14},"C","供货方式、到达地点及收货单位的地址、账号",{"key":22,"text":23,"correct":24},"D","必要的专利技术证书",true,"加工订货计划的具体形式是订货明细表，它不包括必要的专利技术证书内容。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)专业管理实务 岗位知识","建筑工程",0]