[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1161493":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1161493,822,1,"单选题","工程材料成本的盈亏主要核算（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","量差和价差",true,{"key":16,"text":17,"correct":18},"B","采购费和储存费",false,{"key":20,"text":21,"correct":18},"C","运输费和采购费",{"key":23,"text":24,"correct":18},"D","仓储费和损耗费","工程材料成本的盈亏主要考核材料的量差和价差这两个方面。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)专业管理实务 岗位知识","建筑工程",0]