[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1161491":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1161491,822,1,"单选题","根据“建筑安装工程费用组成”的规定，下列费用（ ）不属于直接工程费。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","人工费",false,{"key":16,"text":17,"correct":18},"B","措施费",true,{"key":20,"text":21,"correct":14},"C","施工机具使用费",{"key":23,"text":24,"correct":14},"D","材料费","措施费不属于直接工程费。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)专业管理实务 岗位知识","建筑工程",0]