[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1161397":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1161397,822,1,"单选题","按（ ）实行限额领料，易出现某分项工程节约较多，另外分项工程节约较少甚至超耗的现象。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","配套机械",false,{"key":16,"text":17,"correct":14},"B","责任人",{"key":19,"text":20,"correct":21},"C","分项工程",true,{"key":23,"text":24,"correct":14},"D","工程部位","按分项工程实行限额领料，易出现某分项工程节约较多，另外分项工程节约较少甚至超耗的现象。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)专业管理实务 岗位知识","建筑工程",0]