[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1161389":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1161389,822,1,"单选题","材料入库时，材料应按照材料验收程序进行检验，正确的顺序为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","验收前准备、核对验收资料、检验实物、办理入库手续",true,{"key":16,"text":17,"correct":18},"B","验收前准备、检验实物、核对验收资料、办理入库手续",false,{"key":20,"text":21,"correct":18},"C","核对验收资料、验收前准备、验收实物、办理入库手续",{"key":23,"text":24,"correct":18},"D","核对验收资料、办理入库手续、验收前准备、检验实物","材料入库时，材料应按照材料验收程序进行检验，正确的顺序为验收前准备、核对验收资料、检验实物、办理入库手续。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)专业管理实务 岗位知识","建筑工程",0]