[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1161369":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1161369,822,1,"单选题","某投标单位将技术标和商务标分别封装，在封口处加盖本单位公章和项目经理签字后，在投标截止日期前1天上午将投标文件报送业主。次日（即投标截止日当天）下午，在规定的开标时间前1小时，该投标单位又递交了一份补充材料，其中声明将原报价降低4％。但是，招标单位的有关工作人员认为，根据国际上“一标一投\"的惯例，一个投标单位不得递交两份投标文件，因而拒收投标单位的补充材料。开标会由市招投标办的工作人员主持，市公证处有关人员到会，各投标单位代表均到场。结合以上背景资料回答以下问题： 该投标单位运用了（ ）报价技巧。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","多方案报价法",false,{"key":16,"text":17,"correct":14},"B","增加建议方案法",{"key":19,"text":20,"correct":21},"C","突然降价法",true,{"key":23,"text":24,"correct":14},"D","不平衡报价法","由题可知，该投标单位运用了突然降价法报价技巧。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)专业管理实务 岗位知识","建筑工程",0]