[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1161353":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1161353,822,1,"单选题","某投标单位通过资格预审后，对招标文件进行了仔细分析，发现业主所提出的工期要求过于苛刻，现场条件提供有疑问。若要保证实现该工期要求，必须采取特殊措施，从而大大增加成本。因此，该投标单位在投标文件中说明业主的工期要求难以实现，因而按自己认为的合理工期（比业主要求的工期增加6个月）编制施工进度计划并据此报价。结合以上背景资料回答以下问题： 自招标文件发出之日起到投标截止日止，最短不得少于（ ）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","10",false,{"key":16,"text":17,"correct":14},"B","15",{"key":19,"text":20,"correct":21},"C","20",true,{"key":23,"text":24,"correct":14},"D","25","自招标文件发出之日起到投标截止日止，最短不得少于20天。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)专业管理实务 岗位知识","建筑工程",0]