[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1161329":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1161329,822,1,"单选题","施工中遇到连续10天超过合同约定等级的大暴雨天气而导致施工进度的延误，承包商为此事件提出的索赔属于应（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","由承包商承担的风险责任",false,{"key":16,"text":17,"correct":14},"B","给予费用补偿并顺延工期",{"key":19,"text":20,"correct":14},"C","给予费用补偿但不顺延工期",{"key":22,"text":23,"correct":24},"D","给予工期顺延但不给费用补偿",true,"承包商为此事件提出的索赔属于应给予工期顺延但不给费用补偿。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)专业管理实务 岗位知识","建筑工程",0]