[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1161313":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1161313,822,1,"单选题","关于合同双方约定的合同工期的说法，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","包括开工日期",false,{"key":16,"text":17,"correct":14},"B","包括竣工日期",{"key":19,"text":20,"correct":14},"C","包括合同工期的总日历天数",{"key":22,"text":23,"correct":24},"D","合同工期是按总日历天数计算的，不包括法定节假日在内的承包天数",true,"关于合同双方约定的合同工期的说法，正确的是合同工期是按总日历天数计算的，不包括法定节假日在内的承包天数。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)专业管理实务 岗位知识","建筑工程",0]