[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1161312":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1161312,822,1,"单选题","某中央部委以公开招标方式，利用财政资金采购一台技术复杂的实验室分析仪器，达到了政府采购限额标准。该仪器国内有十余家制造商生产。投标截止时，没有供应商投标。经审查，招标文件中没有不合理条款，招标公告及采购程序均符合政府采购相关规定。由于重新公开招标不能满足时间要求，经财政部门批准，可以改变采购方式。结合背景资料回答以下问题： 以上情景中采购人可以采用的采购方式是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","邀请招标",false,{"key":16,"text":17,"correct":18},"B","竞争性谈判",true,{"key":20,"text":21,"correct":14},"C","询价采购",{"key":23,"text":24,"correct":14},"D","单一来源采购方式","由题，以上情景中采购人可以采用的采购方式是竞争性谈判。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)专业管理实务 岗位知识","建筑工程",0]