[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1161300":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1161300,822,1,"单选题","如果投标截止日期前第28天后，由于法律、法令和决策变化引起承包商实际投人成本的增加，应由（ ）给予补偿。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","业主",true,{"key":16,"text":17,"correct":18},"B","承包商",false,{"key":20,"text":21,"correct":18},"C","工程师",{"key":23,"text":24,"correct":18},"D","特殊分包商","业主应该给予补偿。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)专业管理实务 岗位知识","建筑工程",0]