[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1161144":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1161144,821,3,"判断题","在材料采购的过程中，对于不能实现随需随购的材料以及零星够买的材料，应进行分批采购，计划储存。（ ）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"应充分考虑材料购买数量的问题，在材料采购的过程中，对于不能实现随需随购的材料，应进行分批采购，计划储存。对于能够实现零星购买的材料，可以不必批量购买，从而减少存储开支。",{"id":6,"name":21,"category":22,"favorite":23},"(材料员)基础知识","建筑工程",0]