[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1161131":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1161131,821,3,"判断题","施工合同签订时尚未确定或者不可预见的所需材料、设备费为暂估价。（ ）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"本题涉及的考点是暂列金额。暂列金额是指建设单位在工程量清单中暂定并包括在工程合同价款中的一笔款项。用于施工合同签订时尚未确定或者不可预见的所需材料、工程设备、服务的采购，施工中可能发生的工程变更、合同约定调整因素出现时的工程价款调整以及发生的索赔、现场签证确认等的费用。",{"id":6,"name":21,"category":22,"favorite":23},"(材料员)基础知识","建筑工程",0]