[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1161063":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1161063,821,3,"判断题","施工项目的进度控制采用实际进度与计划进度对比的方法，以应急检查为主，定期检查为辅，对进度实施跟踪控制。（ ）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"常用的进度比较方法有：（1）横道图比较法；（2）S型曲线比较法；（3）“香蕉”曲线比较法。",{"id":6,"name":21,"category":22,"favorite":23},"(材料员)基础知识","建筑工程",0]