[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1161061":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1161061,821,3,"判断题","时间参数主要包括流水节拍、流水步距与施工段数。（ ）。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"组织流水施工的时间参数有流水节拍、流水步距和工期。流水节拍是指在组织流水施工时，某个专业队在一个施工段上的施工时间。流水步距是指两个相邻的专业队进人流水作业的时间间隔。工期是指从第一个专业队投入流水作业开始，到最后一个专业队完成最后一个施工过程的最后一段工作，退出流水作业为止的整个持续时间。",{"id":6,"name":21,"category":22,"favorite":23},"(材料员)基础知识","建筑工程",0]