[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1161045":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1161045,821,3,"判断题","依次施工是指把施工对象划分成若干部分，组织同一施工过程的不同班组在各部分同时开始平行作业。（ ）。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"把施工对象划分成若干个施工段，每个施工过程的专业队依次连续地在每个施工段上进行作业，以达到连续、均衡施工，这种组织方式被称为依次施工。",{"id":6,"name":21,"category":22,"favorite":23},"(材料员)基础知识","建筑工程",0]