[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1161035":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":19},1161035,821,3,"判断题","项目是指为达到符合规定要求的目标，按限定时间、限定资源和限定质量标准等约束条件完成的，由一系列相互协调的受控活动组成的特定过程。（ ）",[11,15],{"key":12,"text":13,"correct":14},"A","正确",true,{"key":16,"text":17,"correct":18},"B","错误",false,"项目是指为达到符合规定要求的目标，按限定时间、限定资源和限定质量标准等约束条件完成的，由一系列相互协调的受控活动组成的特定过程。",{"id":6,"name":21,"category":22,"favorite":23},"(材料员)基础知识","建筑工程",0]