[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1160857":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1160857,821,2,"多选题","有下列（ ）情形的，建设单位应当按照国家有关规定办理申请批准手续。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","需要临时占用规划批准范围以外场地的",true,{"key":16,"text":17,"correct":14},"B","可能损坏道路、管线、电力、邮电通信等公共设施的",{"key":19,"text":20,"correct":14},"C","需要临时停水、停电、中断道路交通的",{"key":22,"text":23,"correct":24},"D","不需要进行爆破作业的",false,{"key":26,"text":27,"correct":14},"E","法律、法规规定需要办理报批手续的其他情形","ABCE","建设单位应当按照国家有关规定办理申请批准手续：（一）需要临时占用规划批准范围以及外场地的;（二）可能损坏道路、管线、电力、邮电通讯等公共措施的;（三）需要临时停水、停电、中断道路交通的;（四）需要进行爆破作业的;（五）法律、法规规定需要办理报批手续的其他形式。",{"id":6,"name":31,"category":32,"favorite":33},"(材料员)基础知识","建筑工程",0]