[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1160687":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1160687,821,2,"多选题","在工程网络计划中，针对不同的网络计划形式，关键线路有各种不同的表达方式，它可以是指（ ）的线路。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","双代号网络计划中无虚箭线",false,{"key":16,"text":17,"correct":18},"B","双代号时标网络计划中无波形线",true,{"key":20,"text":21,"correct":18},"C","单代号网络计划中工作时间间隔为零",{"key":23,"text":24,"correct":18},"D","双代号网络计划中持续时间最长",{"key":26,"text":27,"correct":14},"E","单代号网络计划中全由自由时差最小工作连起来","BCD","在工程网络计划中，针对不同的网络计划形式，关键线路有各种不同的表达方式，它可以是指双代号时标网络计划中无波形线，单代号网络计划中工作时间间隔为零，双代号网络计划中持续时间最长的线路。",{"id":6,"name":31,"category":32,"favorite":33},"(材料员)基础知识","建筑工程",0]