[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1160681":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1160681,821,2,"多选题","影响施工项目进度的因素有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","人的干扰因素",true,{"key":16,"text":17,"correct":14},"B","材料、机具、设备干扰因素",{"key":19,"text":20,"correct":14},"C","地基干扰因素",{"key":22,"text":23,"correct":24},"D","政策干扰因素",false,{"key":26,"text":27,"correct":14},"E","环境干扰因素","ABCE","影响施工项目进度的因素有人的干扰因素，材料、机具、设备干扰因素，地基干扰因素，环境干扰因素。",{"id":6,"name":31,"category":32,"favorite":33},"(材料员)基础知识","建筑工程",0]