[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1160671":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1160671,821,2,"多选题","质量管理和其他各项管理工作一样，要做到有计划、有措施、有执行、有检查、有总结，可能使整个管理工作循序渐进，保证工程质量不断提高。通常采用PDCA循环方法。PDCA分为四个阶段，即（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","计划",true,{"key":16,"text":17,"correct":14},"B","执行",{"key":19,"text":20,"correct":14},"C","检查",{"key":22,"text":23,"correct":24},"D","总结",false,{"key":26,"text":27,"correct":14},"E","处置","ABCE","质量管理和其他各项管理工作一样，要做到有计划、有措施、有执行、有检查、有总结，可能使整个管理工作循序渐进，保证工程质量不断提高。通常采用PDCA循环方法。PDCA分为四个阶段，即计划、执行、检查、处置。",{"id":6,"name":31,"category":32,"favorite":33},"(材料员)基础知识","建筑工程",0]