[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1160668":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1160668,821,2,"多选题","施工项目质量控制体系建立的原则有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","分层次规划原则",true,{"key":16,"text":17,"correct":18},"B","界面划分交叉原则",false,{"key":20,"text":21,"correct":14},"C","总目标分解原则",{"key":23,"text":24,"correct":14},"D","质量责任制原则",{"key":26,"text":27,"correct":14},"E","系统有效性原则","ACDE","系统建立的原则是：分层次规划原则，总目标分解原则，质量责任制原则，系统有效性原则。",{"id":6,"name":31,"category":32,"favorite":33},"(材料员)基础知识","建筑工程",0]