[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1160662":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1160662,821,2,"多选题","建设工程价款动态结算的方法主要有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","按竣工调价系数结算",true,{"key":16,"text":17,"correct":14},"B","按实际价格结算",{"key":19,"text":20,"correct":21},"C","按预算价格结算",false,{"key":23,"text":24,"correct":14},"D","按调价文件结算",{"key":26,"text":27,"correct":14},"E","按调值公式结算","ABDE","建安工程价款的动态结算就是要把各种动态因素渗透到结算过程中，使结算大体能反映实际的消耗费用。几种常用的动态结算办法包括：1）按实际价格结算法2）按主材计算价差3）竣工调价系数法4）调值公式法",{"id":6,"name":31,"category":32,"favorite":33},"(材料员)基础知识","建筑工程",0]