[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1160659":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1160659,821,2,"多选题","若施工中缺乏设计图中所要求的钢筋，征得设计单位同意后，可按（ ）原则进行钢筋现场代换。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","等强度代换",true,{"key":16,"text":17,"correct":18},"B","等间距代换",false,{"key":20,"text":21,"correct":14},"C","等面积代换",{"key":23,"text":24,"correct":18},"D","等应力代换",{"key":26,"text":27,"correct":18},"E","等刚度代换","AC","若施工中缺乏设计图中所要求的钢筋，征得设计单位同意后，可按等强度代换，等面积代换原则进行钢筋现场代换。",{"id":6,"name":31,"category":32,"favorite":33},"(材料员)基础知识","建筑工程",0]