[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1160641":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1160641,821,2,"多选题","模板的拆除程序一般为（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","先支后拆",true,{"key":16,"text":17,"correct":18},"B","先支先拆",false,{"key":20,"text":21,"correct":14},"C","后支先拆",{"key":23,"text":24,"correct":18},"D","后支后拆",{"key":26,"text":27,"correct":14},"E","非承重部分先拆后拆除承重部分","ACE","模板的拆除程序拆除模板应按方案规定的程序进行，先支的后拆，先拆非承重的部分。",{"id":6,"name":31,"category":32,"favorite":33},"(材料员)基础知识","建筑工程",0]