[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1160334":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1160334,821,1,"单选题","材料采购计划是（ ）根据所编制的主要材料、大宗材料计划、市场供应信息等，由（ ）物资部门做出订货或采购计划。（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工单位施工单位项目部",false,{"key":16,"text":17,"correct":18},"B","工程项目部施工单位物资部门",true,{"key":20,"text":21,"correct":14},"C","施工单位物资部门施工单位项目部",{"key":23,"text":24,"correct":14},"D","建设单位施工单位物资部门","建筑材料采购的内容包括：确定工程项目材料采购计划及材料采购批量。材料采购计划是工程项目部根据所编制的主要材料、大宗材料计划、市场供应信息等，由施工单位物资部门做出订货或采购计划。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)基础知识","建筑工程",0]