[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1160284":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1160284,821,1,"单选题","某建筑工程编制招标控制价。已知工程设备费为0，分部分项工程费400万元，单价措施项目费32万元，总价措施项目费18万元，暂列金额10万元，暂估材料15万元，专业工程暂估价20万元，总承包服务费2万元，计日工为0；根据背景资料，回答并计算下列问题： 实行工程量清单计价的招标工程，对于投标人来说施工图预算表现为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投标报价",true,{"key":16,"text":17,"correct":18},"B","招标控制价",false,{"key":20,"text":21,"correct":18},"C","设计概算",{"key":23,"text":24,"correct":18},"D","合同价","实行工程量清单计价的招标工程，对于投标人来说施工图预算表现为投标报价。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)基础知识","建筑工程",0]