[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1160274":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1160274,821,1,"单选题","在现行定额不能满足需要的情况下，出现了定额缺项，此时可编制（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","预算定额",false,{"key":16,"text":17,"correct":14},"B","概算定额",{"key":19,"text":20,"correct":21},"C","补充定额",true,{"key":23,"text":24,"correct":14},"D","消耗量定额","补充定额是指在现行定额不能满足需要的情况下，为了补充缺项所编制的定额，在指定的范围内，可作为以后修改定额的依据。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)基础知识","建筑工程",0]