[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1160261":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1160261,821,1,"单选题","工程量清单的项目编码应采用十二位阿拉伯数字表示，其中第五、六位数字的含义是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","附录分类顺序码",false,{"key":16,"text":17,"correct":18},"B","分部工程顺序码",true,{"key":20,"text":21,"correct":14},"C","专业工程代码",{"key":23,"text":24,"correct":14},"D","分项工程项目名称顺序码","项目编码是分部分项工程量清单项目名称的数字标识。以\\\"五级编码\\\"用十二位阿拉伯数字表示。其中第五、六位数字的含义是分部工程顺序码。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)基础知识","建筑工程",0]