[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1160176":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1160176,821,1,"单选题","已知双代号网络计划中，某工作有两项紧前工作，它们的最早完成时间分别为18天和23天。如果该工作持续时间为6天，则该工作最早完成时间为（ ）天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","18",false,{"key":16,"text":17,"correct":14},"B","23",{"key":19,"text":20,"correct":14},"C","24",{"key":22,"text":23,"correct":24},"D","29",true,"工作最早开始时间等于各紧前工作的最早完成时间的最大值，题目中某工作有两项紧前工作，最早完成时间的最大值为23天，则该工作最早开始时间等于23天。该工作最早完成时间等于最早开始时间加上其持续时间23+6＝29天，故选项D正确。",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)基础知识","建筑工程",0]