[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1160170":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1160170,821,1,"单选题","已知某项目的费用偏差大于0，进度偏差小于0。那么已完工作实际费用（ACWP）,计划工作预算费用（BCWS）和已完工作预算费用（BCWP）三个参数的关系为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","BCWP>ACWP>BCWS",false,{"key":16,"text":17,"correct":18},"B","BCWS>BCWP>ACWP",true,{"key":20,"text":21,"correct":14},"C","BCWS>ACWP>BCWP",{"key":23,"text":24,"correct":14},"D","BCWP>BCWS>ACWP","费用偏差（CV）=已完工程计划费用（BCWP）-已完工程实际费用（ACWP）>0，即：已完工程计划费用（BCWP）>已完工程实际费用（ACWP）②进度偏差（SV）=已完工程计划费用（BCWP）-拟完工程计划费用（BCWS）BCWP>ACWP",{"id":6,"name":27,"category":28,"favorite":29},"(材料员)基础知识","建筑工程",0]